Center Registry · Georgia

Core Scientific Dalton Campus

Core Scientific · Dalton, Whitfield County, Georgia

Verified by Center RegistryChecked against 4 sources, including primary filings and releases
Open on the map →
295 MW
Critical IT planned
75 MW
Energized today
2018
First power
SERC
Grid region · location approximate
In brief

What makes it notable.

  1. A conversion of Core Scientific's own powered mining campus (2018 era) to high-density HPC colocation, with Phase I fully handed over and the first billable capacity in the first quarter of 2026.
  2. Dalton Utilities supplies up to 120 MW at the Boring Drive site and up to 50 MW at Industrial South, expanded since for the HPC buildout. About 75 MW is live against 295 MW critical planned.
  3. The full 175 MW allocation is targeted for early 2027, and the other 120 MW at the campus is now leased, with first delivery estimated for the second half of 2027.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Dalton Utilities
Site and build
Core Scientific (self-performed)
Compute
NVIDIA
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2018First powermining); 2026-Q1 (first HPC billable capacity
  2. Nov 2026Today
  3. 2027Full buildoutearly: the full ~175 MW CoreWeave allocation); 2027-H2 initial neocloud delivery
The detail

Each party's role.

Power

Dalton Utilities. Municipal utility; electric service agreements supply up to 120 MW at the Boring Drive site and up to 50 MW at Industrial South, expanded since for the HPC buildout

Site and build

Core Scientific (self-performed). Converting its own powered mining campus (2018-era) to high-density HPC colocation; Dalton Phase I fully handed over in Q1 FY2026

Compute

NVIDIA. GPU infrastructure for CoreWeave AI cloud workloads; DGX hardware reported at Dalton 1 reported

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.

Need capacity in Georgia?

Looking for GPU colocation or a campus in Georgia? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.

Tell us what you need →