Core Scientific Muskogee Campus

Core Scientific · Muskogee, Muskogee County, Oklahoma

Verified by Center RegistryChecked against 4 sources, including primary filings and releases
Open on the map →
1,000 MW
Critical IT planned
70 MW
Energized today
2026
First power
SPP
Grid region · location approximate
In brief

What makes it notable.

  1. A campus at Port Muskogee's John T. Griffin Industrial Park that grew to about 1.5 GW gross after Core Scientific closed the Polaris DS acquisition on August 13, 2026, bringing about 440 MW of in-service capacity under OG&E agreements.
  2. The first building is greenfield, designed for the NVIDIA GB300 platform with high-density liquid cooling, at 100 MW gross or 70 MW critical IT. Ground broke in November 2024, and the first building was complete and billing by November 2026.
  3. The plan reaches 1,000 MW critical across the expanded site, with full buildout stretching into 2027 and beyond rather than a single delivery date.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Oklahoma Gas & Electric (OG&E), Southwest Power Pool (SPP), Port Muskogee
Site and build
Core Scientific
Compute
NVIDIA GB300
Cloud operator
CoreWeave
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Nov 2026Today
  2. 2026First powerfirst ~70 MW building billing to CoreWeave as of 2026-11-05
  3. 2027+Full buildout
The detail

Each party's role.

Power

Oklahoma Gas & Electric (OG&E). Retail utility serving the campus; the ~440 MW of in-service gross capacity under OG&E electric service agreements came with the Polaris DS acquisition (closed 2026-08-13 per the 10-Q, ~$444M cash, plus a $40M contingent payment if an extra 40 MW of firm power arrives before 2026-12-31)

Power

Southwest Power Pool (SPP). Regional transmission organization for the OG&E footprint

Power

Port Muskogee. Port authority: land and site-infrastructure host (John T. Griffin Industrial Park)

Site and build

Core Scientific. In-house design, build and operations of the greenfield HPC halls (100 MW gross = 70 MW critical IT); high-density liquid cooling for the NVIDIA GB300 platform, vendor undisclosed

Compute

NVIDIA GB300. First building designed for the NVIDIA GB300 platform

Cloud operator

CoreWeave. AI cloud platform / orchestration running on the hosted GPUs

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.