401 MW
Critical IT planned
0 MW
Energized today
2027-Q4
First power
MISO
Grid region · location approximate
In brief

What makes it notable.

  1. A brownfield redevelopment of the former Century Aluminum smelter on roughly 750 acres in Hawesville, Kentucky, reusing the inherited interconnect of about 482 MW.
  2. Big Rivers Electric supplies retail and MISO power, with Kenergy as the delivery cooperative, and 401 MW of critical IT is planned.
  3. TeraWulf handles facility operations and management, and Fluor is the EPC contractor for the three buildings. First power is targeted for the fourth quarter of 2027 and full buildout for the second quarter of 2028.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Big Rivers Electric Corporation, Kenergy Corp
Site and build
Fluor Enterprises, TeraWulf
Compute
Accelerator vendor undisclosed
Cloud operator
TeraWulf, Anthropic
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Nov 2026Today
  2. 2027-Q4First powerCB-1 ready for service
  3. 2028-Q2Full buildoutdeliveries begin late 2027 and conclude Q2 2028
The detail

Each party's role.

Power

Big Rivers Electric Corporation. Retail + MISO supply over the inherited ~482 MW smelter interconnect

Power

Kenergy Corp. Retail-delivery co-op (Big Rivers/MISO power)

Site and build

Fluor Enterprises. EPC contractor on a guaranteed-maximum-price basis for the three data center buildings (definitive agreement, Nov 2026)

Site and build

TeraWulf. Brownfield redevelopment of the former Century Aluminum smelter (~750 acres); direct-to-chip liquid cooling assumed, EPC/cooling partner not disclosed inferred

Compute

Accelerator vendor undisclosed. Not yet selected; Anthropic runs NVIDIA, Trainium and TPUs inferred

Cloud operator

TeraWulf. Data center facility operations and management

Cloud operator

Anthropic. Runs its own AI training and inference stack as the tenant workload

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.

Need capacity in Kentucky?

Looking for GPU colocation or a campus in Kentucky? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.

Tell us what you need →