Crusoe · Abilene, Taylor County, Texas
Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.
Behind-the-meter on-site power plant. ~900 MW on-site generation + BESS; ERCOT-connected
ERCOT. Interconnected grid region
Closed-loop non-evaporative liquid cooling. Cooling for ultra-high-density compute (greenfield build, no retrofit)
Undisclosed (Microsoft-procured). Vendor undisclosed; NVIDIA or Microsoft Maia inferred
Crusoe. Builds and operates the AI factory campus
Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.
Looking for GPU colocation or a campus in Texas? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.