Chirisa Technology Parks / PowerHouse Data Centers · Chester, Chesterfield County, Virginia
Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.
Dominion Energy. Utility power on the PJM grid, via the Meadowville substation
PowerHouse Data Centers (a division of AREP). Developer/operator; direct-to-chip liquid cooling. Building 1 was a retrofit of a former Capital One facility
Chirisa Technology Parks. Campus owner/developer
NVIDIA H200. ~10,224 H200 on InfiniBand (Phase 1) reported
CoreWeave. AI/HPC cloud orchestration running the leased capacity
Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.
Looking for GPU colocation or a campus in Virginia? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.