200 MW
Critical IT planned
0 MW
Energized today
2027-Q4
First power
WECC
Grid region · location approximate
In brief

What makes it notable.

  1. A 144 MW temporary natural gas plant is proposed to bridge the gap until NV Energy can provide permanent service, expected in two to three years. The PUCN application was filed April 20, 2026.
  2. A dedicated on-site substation sits within the project, serving 200 MW critical IT out of 230 MW gross planned.
  3. Two two-story buildings on 252 acres have been under construction since May 2026, built in a single phase with a reported fourth-quarter 2027 target.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
NV Energy, South Valley temporary gas plant
Site and build
Fleet Data Centers (build-to-suit)
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Nov 2026Today
  2. 2027-Q4First powerreported target
  3. 2027Full buildoutsingle phase, 100% pre-leased
The detail

Each party's role.

Power

NV Energy. Utility; permanent service expected in 2 to 3 years; dedicated on-site substation within the bond-financed project reported

Power

South Valley temporary gas plant. 144 MW temporary natural gas plant to bridge interconnection; PUCN application filed 2026-04-20 reported

Site and build

Fleet Data Centers (build-to-suit). Greenfield on 252 acres; dual two-story buildings under construction since May 2026; GC not named reported

Compute

Not disclosed. Tenant-controlled inferred

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.

Need capacity in Nevada?

Looking for GPU colocation or a campus in Nevada? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.

Tell us what you need →