Novva Data Centers · West Jordan, Salt Lake County, Utah
Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.
Rocky Mountain Power (PacifiCorp). Retail utility; on-campus 200 MW substation, but cannot fully serve until ~2031
On-site natural gas generation. On-site primary power: 200 MW gas plant + 72 permitted engines; solar planned
Novva (BASX Solutions cooling). Water-free ambient-air design with direct-to-chip cooling (~84% less water than comparable regional data centers, PUE 1.18 annualized); 100-acre, ~1M sq ft campus reported
Not disclosed. Tenant-controlled inferred
Not disclosed. Tenant-controlled inferred