Center Registry · Wyoming

Related Digital Cheyenne

Related Digital · Cheyenne, Laramie County, Wyoming

Verified by Center RegistryChecked against 4 sources, including primary filings and releases
Open on the map →
302 MW
Critical IT planned
0 MW
Energized today
2026-Q4
First power
WECC
Grid region · location approximate
In brief

What makes it notable.

  1. A 302 MW planned greenfield campus on 115 acres in Cheyenne, with Clayco as construction manager on a $1.2B first phase and first power estimated for the fourth quarter of 2026.
  2. Black Hills Energy serves it under Wyoming's Large Power Contract Service tariff with no retail rate impact, and Related invested about $20M in a new transformer and substation expansion.
  3. The tariff requires behind-the-meter backup: batteries with roughly seven minutes of ride-through plus generators. Cooling is closed-loop direct-to-chip with air-cooled chillers and nominal water use.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Black Hills Energy, On-site backup (BESS + generators)
Site and build
Clayco (Clayco Compute)
Compute
Not disclosed
Cloud operator
CoreWeave
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Nov 2026Today
  2. 2026-Q4First powerestimated from the phase 1 completion target
  3. phased, not disclosedFull buildout
The detail

Each party's role.

Power

Black Hills Energy. Regulated electric provider under the Wyoming Large Power Contract Service tariff (no rate impact on retail customers); Related invested ~$20M in a new transformer and substation expansion

Power

On-site backup (BESS + generators). Behind-the-meter dispatchable backup required by the tariff; roughly 7-minute battery ride-through plus generators reported

Site and build

Clayco (Clayco Compute). Construction manager, fast-track greenfield build on 115 acres ($1.2B phase 1); closed-loop direct-to-chip liquid cooling rejecting heat via high-efficiency air-cooled chillers, nominal water use

Compute

Not disclosed. Tenant-deployed; no chip vendor named inferred

Cloud operator

CoreWeave. Tenant runs its own AI cloud stack on the leased capacity inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.

Need capacity in Wyoming?

Looking for GPU colocation or a campus in Wyoming? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.

Tell us what you need →